Rehabilitation of South Aghwar Irrigation / Phase 1

PROJECT DETAILS

 

Contract name: Rehabilitation of South Aghwar Irrigation / Phase 1 No.113/2013
Commencement Date :15/03/2014
Completion Date: 07/12/2016
Description: The project includes the rehabilitation of the existing asbestos irrigation networks through execution of 110,000 meters of HDPE pipes ranging from 630 mm. diameter to 90 mm. diameter as follows:
– 700 m. of 630 mm. diameter.
– 3,400 m. of 500 mm. diameter.
– 10,200 m. of 450 mm. diameter.
– 3,200 m. of 400 mm. diameter.
– 7,200 m. of 355 mm. diameter.
– 7,350 m. of 315 mm. diameter.
– 10,750 m. of 280 mm. diameter.
– 11,900 m. of 225 mm. diameter.
– 21,800 m. of 160 mm. diameter.
– 22,800 m. of 110 mm. diameter.
– 10,700 m. of 90 mm. diameter.
The project also includes rehabilitation of the existing tanks, channels, replacement of water filters, pumps, valves, FTA’s, and related electrical works.
Amount of contract: 12,766,197.180 USD

Name of Employer: Jordan Valley Authority